H and M Company hypertrack Page 8
TOWN OF FLORIDA, NY:
1.4 million square feet substantially complete
in just a few short weeks from the start of the foundation work.
KMART
11-14-01
5 weeks after the start of foundations.
12-3-01
5 weeks after the start of steel erection.
11-21-01
3 weeks after the start of steel erection
800,000 square feet erected and decked;
7 days after the start of panel erection.
2-1-02
14 weeks after the start of foundations
H+M achieves substantial completion.